A delta needs an observatory before it needs a wall

The Ebro Delta is losing ground on its open coast. The first response should be cheap, repeatable measurement, with clear triggers for the larger works.

A boardwalk and beach houses undermined by storm erosion
Photo: Beach erosion after a storm, New York. Ed Edahl, Public domain, via Wikimedia Commons.

About 26,600 hectares of the Ebro Delta plain sit at or below one metre in the satellite surface model. Between 2017 and 2025, 64 hectares were lost to the sea at Fangar and the river mouth. Mean temperature over 1996–2025 is 1.2 °C higher than over 1950–1979, and days at or above 30 °C are nine times as frequent.

Numbers like these invite a large answer: a seawall, a programme of hard defences. Our study points the other way.

Start with what is cheap and repeatable

Every figure in the study came from open data: Sentinel-2 images, a public elevation model, ERA5 climate records and species records from GBIF. That means the same analysis can be repeated every year at low cost.

We recommend a Delta Observatory that does exactly that: shoreline, land, flooded paddies, rice, climate and species, verified and published as an annual bulletin. It is the measure that makes every other decision better informed.

Soft measures first, with triggers for the rest

On the open coast, restoring dunes and wetlands gives sand somewhere to stay and birds somewhere to nest. On the Trabucador bar, sand nourishment and dune planting keep it above storm water while its movement is monitored.

The root cause, sediment held behind upstream reservoirs, needs a slower and costlier study. The observatory tells you when that study can no longer wait.

What this means for other deltas and coasts

Screening-level evidence will not set engineering design values, and our report says so. What it does is show where to look and what to ask, quickly and in public. For most low-lying coasts, that is the right first step.

Source

The Ebro DeltaA coast on the move. Tessera case study, 88 pages, November 2026.

Figures are Tessera calculations from open data, or official statistics quoted as published. Questions about a number? Contact us.

Start a project

Bring us the question

Tell us about the site, the programme or the decision ahead. A few sentences are enough to start.

Describe your project